Contractors working on the Puget Island bridge have returned to work for the season and are painting pier supports, doing touch up work and replacing walkway decking.
The bridge's steel structure has received three coats of paint. Workers for the prime contractor, Royal Bridge, Inc., are working with a subcontractor, Structural Coatings.
Royal Bridge has been sand blasting and painting Pier 16 (see photo); work was to have been completed last week, Tamara Greenwell, regional communicatins director for the Washington State Department of Transportation reported last week.
The abrasive cleaning and painting continues on Piers 17 and 18.
Meanwhile, Structural Coatings is cleaning and painting areas where rigging was installed for the containment curtains.
"Royal Bridge anticipates that the painting will be completed before the end of the year," Greenwell said. "That said, the work is weather dependent.
" Currently Royal Bridge is only anticipating two nights of closure associated with the paving activities on the deck. The closure dates have not been determined yet, and will not occur for at least another month."
The night time closures for deck work last year lasted from 9 p.m. to 5 a.m. During that time the Wahkiakum County Ferry Oscar B. was in operation, and emergency responders staged equipment on the Island for rapid response.
Greenwell said that 200 of the 380 total working days have been charged as of April 19, and 58.5 of the 70 total bridge closures have been charged.